January 2012
Planning and setting-up
Online induction

Finalisation of project plan and contracts
Attend online Induction
Join online collaborative space
Submit project plan
Contracts finalised
(40% milestone payment)
February 2012
Research and preparation
Setting up research preparation activities

Developing, sharing and comparing consultation, measurement and analysis tools in online collaborative space
Participate in online collaborative activities
March-April 2012
Collection and analysis
Online meeting
Sharing consultation
Collecting and analysis of data
Write up draft findings report
Attend online meeting
Participate in online collaborative activities
Present draft report
May-June 2012
Reporting
F2F meeting (Melbourne), present project findings, write final report
Attend f2f meeting
Participate in online activities
Submit final report
(60% milestone payment)

Payment schedule


There will be two payments (as per Schedule 4 of the contract):

1
40% at signing of contract
Commencement payment
2
60% at acceptance of final project report
Final payment

Invoices can be submitted via email to the Project Lead (Bronwyn Lapham), but should be addressed to:

eWorks
Level 5, 437 St Kilda Road
Melbourne Vic 3004

Please include a reference to the project (Learner Pathways, E-portfolios Exemplar Project), and which payment you are claiming.